Karen's house project @133 OhioThe plansThe point of the project is to open up the back of the house to the morning light. This necessitated moving the stairs to the basement. This prompted re-arranging interior walls and offered the opportunity for a u-shaped kitchen and peninsula. The illustrations below are not on the same scale. If you have trouble making them out, please let me know. The changes | ||||||||||||||||||||||||||||||||||||||||||||||||||||
|
What is the plan, man? Phase 1: Preparation leading up to demolition that began June 12 |
|||
| Phase 2: Down to the bones | |||
| Demolition June 12-16 |
Siding June 14-16 |
Excavation June 17 |
Waiting for
concrete June 18-?? |
Phase 3: Foundation work begins; inside shored up; toilet flushes |
|||
| Inside June 23-July 3 |
Outside June 23-July 3 |
Ah,
running water June 23-July 3 |
|
| Phase 4: Stairway to heaven is no flight of fancy | |||
| Basement
becomes accessible July 3-10 |
|||
| Phase 5: Framing, siding | |||
| Taking sides July 14-22 |
Framing analysis July 14-22 |
Lift
high the roofbeam, carpenters July 14-22 |
|
| Phase 6: Windows, doors, decks, electricity, deck joists, drywall | |||
| Exploring the
interior July 22-Aug. 13 |
Shower
is working August |
Plumbing the
depths July 22-Aug. 13 |
Dare to drywall Aug. 14 |